Monk Furniture prepares for Holiday Inn Express

    150 150 Daniel Fountain
    • 0

    Monk Furniture is currently in the final stages of preparation for phase one installation of furniture at the new holiday Inn Express at Heathrow.After a lengthy qualification process and against some strong competition Monk Furniture successfully won the contract for furniture at this new site ahead of the previous well established supplier.

    Starting work back in October 2009 the order was awarded in March this year, with a successful sample room installed in April and phase one due to be installed in the second half of June.

    Once completed this will be the largest Holiday Inn Express in Europe with 300 rooms, all of which are having furniture supplied by Monk.

    Phase one involves 124 rooms with the remaining 176 scheduled for September.

    From designs and briefs received from the Contractor Monk Furniture translated all the information into practical, workable and impactful product.

    All the furniture items for this contract are being produced in Egger MFC, including Eurolight, are being manufactured on our premises in Macclesfield and will be installed by our own fully qualified team.

    Daniel Fountain / 31.05.2010

    Editor, Hotel Designs